Numurkah Northern Levee

  • Project typeNumurkah Levee Stage 1 Northern Levee
  • Project value$3.5 million
  • Project scheduleWorks Commencing Station Street and Numurkah Depot.
  • Contractor nameMick Hogan Excavations
Numurkah-Northern-Levee-Web-Image.jpg

The Town of Numurkah has experienced significant flood events that have impacted the community greatly. Moira Shire Council has recognised these challenges and has prioritised flood mitigation efforts to safeguard residents and their homes.

The Numurkah Northern Levee Project aims to provide robust protection against major flood events, ensuring the safety and resilience of our community. 

The Northern Levee

The Northern Levee is the first stage of a broader flood mitigation initiative designed to reduce the risk of flooding in Numurkah.

This critical infrastructure project will construct a 3.12km levee from the Goulburn Valley Highway to Kinnairds Road, incorporating a mix of earthen embankments and concrete retaining walls.

This project has been developed in collaboration with the Numurkah Flood Mitigation Implementation Committee, ensuring that community input and expectations are integrated into the design. 

Construction Schedule

The Numurkah Northern Levee construction will be delivered in stages across multiple locations. Timings are approximate and subject to change due to weather or unforeseen circumstances.

Stage A

1 May – 30 July 2025
From Station Street along the wetlands to the area adjacent to the Council Depot, including the track behind the golf course to Kinnairds Road.

Stage B

6 June – 30 July 2025
Section between the railway line and Station Street, and from the Council Depot to Brenion Street.

Stage C

1 July – 30 September 2025
Brenion Street between Meiklejohn Street and McCaskill Street.

Stage D

15 July – 24 November 2025
Gray Street.

Stage E

28 August 2025 – 24 January 2026
Inside the Council Depot, and from the Goulburn Valley Highway to the railway line.

Practical completion of the levee is expected in early 2026.

 

UPDATES

May 2025 - Statement from Moira Shire Council Chief Executive Officer Matthew Morgan

It’s fantastic to see work getting underway on one of Numurkah’s most significant and long-anticipated projects. This marks a major milestone for Numurkah, and we look forward to seeing this important infrastructure take shape over the coming months.

We’ve planned construction in staged segments to reduce disruption as much as possible for residents, traffic and local businesses. Some sections of walking tracks will be temporarily closed and fencing will be in place during heavy machinery works, and we’ll ensure access is restored as soon as it’s safe to do so.

Traffic management, including lane closures and parking changes, will be in place along sections of the levee when construction is happening in that area, particularly when works reach the Melville Street intersection. We ask people for their patience while works are being completed, and we are working to minimise disruption as much as possible.

We’re also basing project design on sustainability principles. More than 5000 cubic metres of soil excavated as part of the Patterson Street Basin Upgrade project has been diverted from landfill and treated to improve quality, so it can be be reused as part of the levee construction.

 

May 2025 

Construction on the Numurkah Northern Levee began on 1 May 2025, starting near the Settlement Pond walking track. Excavation is complete, and levee bank material is being placed and compacted. The walking track is expected to reopen next week.

Works will then move from Kinnairds Road toward Madigan Street carpark. This section will be closed due to heavy machinery, and Council is working with community groups on alternate walking routes.

Traffic management plans are being finalised, especially around Melville Street. Road closures will be avoided where possible but may occur at night for safety.

A Yorta Yorta cultural heritage monitor is on site near Kinnairds Road to ensure culturally sensitive works.

APRIL 2025

Construction preparation for the Numurkah Northern Levee has begun, marking a major step in protecting the town from future flood events. The project will deliver critical levee infrastructure along the northern edge of Numurkah to reduce flood risk and improve community resilience. Works are being led by Council in partnership with the Victorian and Australian governments.

Read the full media release for more details: Construction begins on Numurkah levee project

 

FAQs