Paterson and Russell Street Numurkah Road and Drainage Improvement

  • Project typeRoads and Drainage
  • Project valueStage 1 - $450,000
  • Project scheduleStage 1 to commence soon
  • Contractor nameTender under application
Paterson-Russel-Moira-Shire-Project.jpg
The Paterson and Russel Street drainage area in Numurkah is home to more than 300 residential properties and is prone to experience flash flooding, damaged roads, and barriers for pedestrian accessibility.
Council plans to address these concerns by conducting a 5-stage approach to improve the drainage, road pavement and pedestrian access. 

The overall project will deliver:

  • Larger drainage infrastructure in the storm water catchment
  • Road surface changed to ashphalt to reduce surface deflection and improve quality
  • Improved footpaths widened to 1.5m for greater accessibility
  • Construction of a new kerb and channel
  • Redesigned street scape including new trees  
 

Stage 1 works are expected to commence in June 2024 and involve: 

  • Expansion of the existing basin from 4ML to 9.4ML to ensure enough storm water storage
  • Removal of existing vegetation as required for the expansion and planting of new streetscape including indigenous vegetation
  • Upgrade of pump outlet 
  • Construction of high flow spillway to prevent the basin overflowing into the residential streets 
Traffic management will be in place at the time of the works to minimise disruptions to traffic and ensure a safe worksite for workers and the community. 

Paterson-Russell-Stage-1-plan.pdf(PDF, 1MB)

Stage 1 was successful in receiving a $400,000 funding through the Local Community and Regional Infrastructure program from the Federal Government. 
The total cost of works for Stage 1 is estimated to $450,000. 

 

Paterson and Russell Street 5 Stage Project

Due to the significant investment in the community to complete the project, Council is proposing to split the works into 5 stages. This will allow minimal disruptions to residents, other services across the shire and budget considerations.

 

The proposed stages involve:

Stage 1 - Basin upgrade
Road and Drainage detailed design 
Stage 2 – Paterson Street between Saxton and O’Connor
Stage 3 – Russell Street between Saxton and O’Connor 
Stage 4 - Paterson Street between O’Connor and McGregor 
Stage 5 – Russell Street between O’Connor and McGregor

 

For More Information

For further information you can request to speak to Moira Shire’s Engineering Department by calling Customer Service on (03) 5871 9222 or send an email to info@moira.vic.gov.au
 
If you would like to be kept inform on project updates you can subscribe to this project page for notifications, subscribe at the bottom of the page. 

 

Project Updates:

Location

Paterson Street, Numurkah 3636  View Map

Google Map