By COB 11 January 2019, 25% or 1,200 tonnes of the Numurkah tyre pile has been removed.

  • We have ramped up to 8 B-Doubles per day (120 tonnes).
  • Weather impact - the pre-christmas rain had no impact and the clean up remains on track.
  • Work stopped on Friday 4 January due to the total fire ban.

Tyres2.jpg     Lifting tyrs 11Jan2019.jpg     TyresMel.jpg

19 December 2018 update

Tyre2.JPG     893719b8-fbff-488c-b8e8-bda0bbd78379.jpg     

What is happening at the Numurkah tyre stockpile site?

Moira Shire Council and the Environment Protection Authority Victoria (EPA) are undertaking the removal of a stockpile of inappropriately stored tyres from a site in Saxton Street, West Numurkah, to ensure the safety of the local community.

While this work is underway to remove the approximately 5,000 tonne stockpile, we are asking the community to please take notice of any safety signage and avoid the site as there will be trucks and heavy machinery in operation.

Access to the site will be restricted for safety reasons. 

Numurkah-25 Saxton St West_0027 (00000002).jpg

Media Releases

Moira moves to remove Numurkah tyre pile - 6 December 2018.

Supreme Court rules on Numurkah tyre dump - 1 October 2018. 

Tyres.JPG     Capture.JPG

No results found. Please try searching again.